PROJECT BUDGET
ARENA

Element Description Arena Costs

A. Site Services
B. Sitework
C. Concrete
D. Masonry
E. Metals
F. Wood and Plastic
G. Thermal and Moisture Protection
H. Doors and Windows
I. Finishes
J. Specialities
K. Equipment
L. Furnishings
M. Conveyance
N. Mechanical Systems
O. Electrical Systems

SUBTOTAL TRADE COSTS

$ 2,349,450
$ 3,354,385
$ 16,477,363
$ 3,865,117
$ 8,285,809
$ 1,145,459
$ 2,926,712
$ 3,047,349
$ 5,678,025
$ 1,024,183
$ 1,086,450
$ 2,642,699
$ 772,800
$ 13,125,000
$ 8,954,348

$ 74,735,115
   

Project Escalation
CM Fees and General Conditions
Tax Credit
Design Continency (1%)
Owner Contingency (4%)
Construction Contingency (5%)

SUBTOTAL CONSTRUCTION INCIDENTALS

$ 750,000
$ 6,633,067
$ 300,000 -
$ 818,182
$ 3,272,727
$ 4,090,909

$ 15,264,885
   
SUBTOTAL CONSTRUCTION COSTS

Inspection and Testing
Design Fees
FF&E (Furniture, Fixtures and Equipment)
WSSC Assessments and Utility Fees
University and MSA Costs
Feasibility Study
$ 90,000,000

$ 600,000
$ 7,300,000
$ 2,000,000
$ 1,000,000
$ 200,000
   
SOFT COSTS


ESTIMATED ARENA PROJECT COSTS
$ 11,900,000


$101,900,000
   

Back to Capital Projects